Thames Tower Reading

Thames Tower

commercial building

Design and build fast-track office fit-out and refurbishment project.

PROJECT WORK

DESIGN & BUILD : HVAC, MECHANICAL & ELECTRICAL SERVICES

LOCATION

READING

PROJECT VALUE

£1.4m

£1.4m

PROJECT VALUE

We carried out this design and build office fit-out project as quickly as possible up against tight deadlines.

G

GROUND FLOOR

This fit-out included starting from a bare empty shell on the ground floor. With strip-out and refurbishment carried out to floors 1 and 2.

08/18

AUGUST 2018

Project successfully completed in August 2018.

Project Details

  • Strip-out and refurbishment of 1st and 2nd floor areas with revised floor layouts.
  • Full fit-out of ground floor empty shell.
  • First and second floor heating and cooling provided by fan coil unit supplied from landlord plant. Ground floor heating and cooling provided by new VRF system.
  • New AHU and control installed in basement to provide ventilation to the ground floor.
  • Air condition systems installed on ground floor and throughout comms rooms.
  • Enhanced access control system installed.
  • BMS control systems modified, expanded and commissioned to take incorporate new services and layouts.